Page 6-10 G1000 System Maintenance Manual – Diamond DA40/40F
Revision G 190-00545-01
6.12.1 Configuration Module Checkout
If the GRS 77 AHRS Configuration Module is replaced:
All three GRS 77/GMU 44 calibration procedures must be performed. Proceed to Section 7.7.
If GDC 74 Configuration Module is replaced:
Configuration settings must be reloaded to the GDC 74A. Proceed to Section 3.5.5.
If GEA 71 Configuration Module is replaced:
Proceed to Section 7.4.2 and check the EGT / CHT indications for accurate readings.
If only the PFD Configuration Module is replaced:
1. Start the G1000 system in configuration mode.
2. Go to the Configuration Upload Page on the PFD.
3. Press the UPDT CFG softkey and press ENT.
If both the PFD and PFD Configuration Module are replaced:
1. The entire G1000 system must be re-configured. Insert the correct G1000 software loader card
into the PFD.
2. Start the G1000 in configuration mode. Go to the System Upload Page on the PFD.
3. See Section 3.5 for instructions on how to use the System Upload page. Check all configuration
files and reload them.
4. After reloading configuration files, examine the G1000 installation for any installed configuration
options. Options are listed in Section 3.4.3.2. Load optional files as necessary.
5. Continue to Section 8 and conduct the return to service checkout.